Value comparison of technological settlement during the construction of a trench-type diaphragm wall and an diaphragm wall with augered piles
Abstract
Value comparison of technological settlement during the construction of a trench-type diaphragm wall and an diaphragm wall with augered piles
Incoming article date: 10.06.2023The comparison of technological settlement values during the construction of various variants of diaphragm wall is presented. Numerical modeling of the construction of a diaphragm wall enclosure was performed in weak water-saturated clayey soils using the Plaxis 3D software package. The investigation results revealed that the technological settlement of the building foundation caused by constructing a trench-type diaphragm wall significantly exceeds the values observed in the construction of a diaphragm wall with augered piles.
Keywords: technological settlement, excavation enclosure, diaphragm wall, numerical modeling, Plaxis